Utica Charging Station EV
Paragraph
Scope of Work:
Install Erosion Control
Mill Existing Asphalt 106,894 sf
Box out Parking Lots 5,128 cy
Install Underground Electric 1,280 LF
Install Storm System CB’s & Piping
Form and Pour Concrete
Heavy Duty Transformer Pad
Sidewalks 2,354 sf
Curb 420 LF
Stanchions for EV Stations 30 Total
Install Erosion Control
Mill Existing Asphalt 106,894 sf
Box out Parking Lots 5,128 cy
Install Underground Electric 1,280 LF
Install Storm System CB’s & Piping
Form and Pour Concrete
Heavy Duty Transformer Pad
Sidewalks 2,354 sf
Curb 420 LF
Stanchions for EV Stations 30 Total