Hazardous Materials, Abatement, & Demolition
Hazardous Materials, Abatement, & Demolition
Swimming Pool Abatement & Demo
Abatement of asbestos and PCB containing materials - including tile thinset, joint sealant and mortar, piping insulation, and transite pipe.
Masonry infills at partitions and construction of temporary partitions to create a corridor for both structure demolition and new construction.
Demolition of a 10,000 Sqft swimming pool and locker room primarily constructed of concrete, masonry, and steel with the footprint of the structure surrounded on three sides with active classrooms, gymnasium, and main corridor.
Installation of a semi-permanent exterior wall weatherproofing system at the three sides of the existing building exposed once the pool structure was removed.
Maine Memorial - Fuel Tank Replacement
Worked with MECSD to determine size and location of underground fuel tank.
Removed existing underground fuel tank per DEC regulations.
Prepped for natural gas conversion.
Gymnasium Abatement & Upgrades
Abated the existing gymnasium flooring system.
Provided a new wood gymnasium flooring system including vented perimeter base with game lines and other relaxed markings.