18 Eldredge St Binghamton City Parks & Rec
Smith Site Development LLC completed the removal and replacement of the existing floor at Binghamton City Parks and Recreation Maintenance Building. The work included demolishing and removal of entire shop failing floor, replacement of subbase to incorporate new floor drainage system and installed wire mesh with heavy duty rated 6” concrete.
Sawcut perimeter of existing floor
Hammer demolished 13,300 sq ft floor
Regraded and added subbase materials
installed wire mesh reinforced with Slip dowels
Sae Cut Control Joints & Caulked expansion Joints
Installed Exterior perimeter insulation
Installed Interior drainage structures
Installed 250 CY of heavy duty concrete