Scope of Work:
Erosion Control Measures
Remove Existing field and failing subbase material
Cut & Fill to Subgrade
Install Underground Field and Stormwater Drainage
Install Concrete Track Trench Drain
Install Field and Track Subbase Material
Install Underground Electrical Lighting
Install Asphalt Track & ADA Parking Spaces
Assisted the Installation New Synthetic Turf Field
Assisted the Installation Rubberized Track
Installed New Spectator Bleachers
Installed Asphalt Parking Lot
Installed Concrete Sidewalks and Specialized Entrances
Landscaping
Install Fence and Gates
Screen & Place Top Soil
Seed and Mulch